[ARCHIVED] Main Street Construction Schedule, October to December 2023

4 workers dress in lime green clothing for safety working on a road surface taken from overhead with

Current Main Street resurfacing ended at the Old Mill; the contractor's goal is to resurface another section up to Buttonball Land before winter ends construction.

Below is an updated tentative schedule for the remaining work from October to the first week in December, when work will cease for the winter.

October 2 - 6

  • Make waterline tie-ins at Pinecrest & Sheffield Rd.
  • Complete drainage structures in front of the Fire Station
  • Complete electrical conduit in front of Egremont Village School

October 10 - 13

  • Complete all waterline house services up to Buttonball Lane

October 16 - 20

  • Excavate roadway & place gravel base from Old Mill to Kenver LTD
  • Begin installing curbing at Rt. 41 to Baldwin Hill Rd South

October 23 - 27

  • Excavate roadway & place gravel base from Kenver LTD to the Village Green
  • Install curbing from Baldwin Hill Rd South to Mom's Cafe

October 30 - November 3

  • Excavate the roadway & place gravel base from Village Green to Buttonball Lane.
  • Excavate Village Green, Sheffield Rd & Buttonball Lane.
  • Fine grade, cut in snow breaks
  • Raise structures from Rt. 41 to the Old Mill
  • Install curbing Mom's Cafe to the Old Mill

November 6 - 10

  • Pave dense grade, base course & binder course
  • Continue raising structures & fine grading for sidewalks
  • Continue waterline house services
  • Install curbing Old Mill to Kenver LTD

November 13 - 17

  • Continue raising structures & fine grading for sidewalks
  • Continue waterline house services
  • Install curbing Kenver LTD to the Village Green

November 20 - 22

  • Continue raising structures & fine grading for sidewalks
  • Complete waterline house services & tie-in new main at GB town line & Creamery Rd.
  • Install curbing Village Green to Buttonball Lane

November 27 - December 1

  • Complete raising structures & fine grading sidewalks
  • Decommission, cut & cap old water main
  • Temporarily patch all sidewalks & trenches

December 4 - 8

  • Adjust hydrants
  • Clean up job for winter shutdown